BC: Change Request is Showing Active Status and Changes are not Being Reflected on the Contract

When a Change Request has an "Active" status but its changes are not reflected on the contract, a specific action is required. The user must select the "Apply to Contract" button on the Change Request. This action will apply the changes to the Billing Contract as intended.

Title
BC: Change Request is Showing Active Status and Changes are not Being Reflected on the Contract
Summary
When a Change Request has an "Active" status but its changes are not reflected on the contract, a specific action is required. The user must select the "Apply to Contract" button on the Change Request. This action will apply the changes to the Billing Contract as intended.
URL Name
BC-Change-Request-is-Showing-Active-Status-and-Changes-are-not-Being-Reflected-on-the-Contract

Release Version
Symptoms
Resolution
Cause
Additional Notes