PSA: Why are the Project Task Assignment Date Changes Not Updating the Assignment Dates?

Project Task Assignment date changes may not update the assignment dates. This occurs if a specific configuration option, 'use-task-based-schedule-creation-strategy', is set to "false". To ensure date changes update the scheduled hours and dates, this setting must be set to "true". Additionally, edits will be ignored if a resource is scheduled for 24 hours or more in a single day.

Title
PSA: Why are the Project Task Assignment Date Changes Not Updating the Assignment Dates?
Summary
Project Task Assignment date changes may not update the assignment dates. This occurs if a specific configuration option, 'use-task-based-schedule-creation-strategy', is set to "false". To ensure date changes update the scheduled hours and dates, this setting must be set to "true". Additionally, edits will be ignored if a resource is scheduled for 24 hours or more in a single day.
URL Name
PSA-Why-are-the-Project-Task-Assignment-Date-Changes-Not-Updating-the-Assignment-Dates

Question
Answer
Additional Notes
Release Version
Was this article helpful?
00
Upload Files
Recommendations
No results for undefined
Loading
Knowledge:PSA: Why are the Project Task Assignment Date Changes Not Updating the Assignment Dates?