Schedule exceptions lost when assigning a held resource request in PSA Work Planner

When a held Resource Request is assigned, any schedule changes made may be overwritten. This occurs if the "Retain Schedule on Assign" setting is not enabled. To preserve schedule modifications, this flag must be enabled within the Assignment Settings.